Solit v Tokai Bank 81
Cal.Rptr.2d 243 Decided January 7, 1999. Mechanic's Liens: To Release
or Not? What exactly does a Release of Mechanic's Lien release? Does
it release just the Mechanic's Lien on file with the County Recorder
-- or the entire right to file a Mechanic's lien in relation to
the project? This issue has plagued construction practitioners for
years. Fortunately, a recent case has resulted in a practical answer that
is workable for all concerned parties. In the recent case of Solit
v Tokai Bank, (1-7-99) 81 Cal.Rptr.2d 243, the court held that a
Release of Mechanic's Lien only extinguished the referenced Mechanic's
Lien and not the entire right to lien the project. This case involved
the construction of the Santa Monica Beach Hotel owned by the Steins
and financed by Tokai Bank. A dispute arose between the Steins and the
project construction manager, Mark Solit. The first Mechanic's Lien
was recorded by Mr. Solit on March 7, 1990; however, no action to
foreclose the Mechanic's Lien was brought within the 90 day statutory
period and thus the lien became void and unenforceable. In August,
1990, the Steins' attorney demanded that Mr. Solit release his lien
voluntarily or be subject to a petition under Civil Code section 3154
ordering the release of the lien. After the demand, Mr. Solit
voluntarily executed a Release of Mechanic's Lien referencing the
March 7, 1990, lien, but subsequently recorded a second Mechanic's
Lien on October 22, 1990. An action was filed between the Steins,
Tokai and Solit. In the action, Solit sought to enforce his lien
of October 22, 1990 (although there was some confusion in the
complaint which made it appear that Solit was attempting to foreclose
on the March 7, 1990 lien). The trial Court ruled that as a matter of
law "Solit's release of the March 7, 1990, lien extinguished all
of Solit's lien rights against the property, thus making any
subsequent liens, including the October 22, 1990, lien
unenforceable." Based on this ruling, the Court dismissed
Solit's complaint to foreclose the Mechanic's Lien, and Solit appealed
this decision. The Appellate Court concluded that Solit's voluntary
release of the stale lien affected only the recorded lien and not his right
to record a subsequent lien. The right to record a lien,
for the same work and materials released in the original lien, is
still limited by the time constraints which control the recording of
any lien. The Court balanced the rights of owners verses those of
contractors in making its decision. The Court commented that in
allowing a Release of Mechanic's Lien to only release the particular
recorded lien, and not the constitutional rights of the contractor,
provided a fair balance between claimants and owners. To hold
otherwise the Court noted, would unfairly favor the owners in that
they would receive a windfall if a contractor filed a lien early and
was forced to release that lien or have it removed by the court upon
the owner's petition. To explain why the Solit case was
necessary and the confusion that previously existed in the
construction industry, we have to look back at the case of Maris
Management Corp. v. Assured Drywall & Textures, (1984) 152
Cal.App.3d 268. In that case, the court held that if a stale
Mechanic's Lien was released by the court after a petition brought by
the owner, then not only was the recorded lien released, but also the
claimant's right to file a lien for that same work and materials was
also released. Thus, the holding of the Maris court lead many
practitioners to believe that if a contractor had its lien released
through a petition of the owner and/or voluntarily recorded a release
of lien, then it was releasing all right to a lien for that
project. The Court in Solit addressed the Maris decision
and concluded that it was wrongly decided. Upon reconsidering this
important issue the Court held that a release of a particular lien is
simply just that, a release of that lien. This decision is important
for all contractors as it provides clear guidance regarding the use of
Release of Mechanic's Lien forms. The Solit decision allows the
early contractor some time to negotiate with the owner after the lien
is filed, and if the statutory time period for filing of a new lien is
still open, the original lien may be allowed to lapse or be released
without waiving the right to lien the project. The Solit
case provides a greater opportunity for negotiation and settlement
rather than forcing early litigation on a project. Based on the Solit
case, to release or not to release is an easier question to answer -- and
is now based solely on the statutory time frames which have always
governed the Mechanic's Lien rights. - This excerpted article was
provided by Theresa Crawford Tate of Crawford & Bangs, West
Covina, California, an ASAC member, and is intended to provide
the reader with general information regarding current legal issues. It
is not to be construed as specific legal advice or as a substitute for
the need to seek competent legal advice on specific legal matters.
American Subcontractors Association California, Inc., P.O. Box 292867,
Sacramento, California 95829-2867 Ph: 888-310-2722 Fax:
530-662-2865 [email protected] http://www.asacalif.com/landmark.htm Contact
Mark Solit: 50 El Castillo, Orinda, CA 94563 925-254-5510
|